In 2008 and 2009 developed decommissioning cost estimates for multiple facilities at Argonne National Labratory in Argonne, Il including four buildings associated with the Intense Pulsed Neutron Source complex; the Alpha Gamma Hot Cell Facility and Building 310.
In 2006 and 2009 developed decommissioning cost estimates for Indiana Michigan Power Company's D.C. Cook Nuclear Power Plant. Cost estimates included numerous scenarios with various spent fuel shipping schedules and decommissioning methodologies.
In summer 2008 worked with Kiewit Federal Group developing a cost estimate for Northwest Energy's Columbia Generating Station main condenser replacement project.
Knight Cost Engineering Services, LLC Phone: 203-788-9353 22 Mt. View Terrace Info@knightces.com New Milford, CT 06776 Last Updated: 3/10/2010